Corporate Office
1511 Sparrow Drive
Nisku, AB Canada T9E 8H9
T: 780.400.3700 | F: 780.400.3701
Manufacturing Facility
1511 Sparrow Drive
Nisku, AB Canada T9E 8H9
T: 780.400.3700 | F: 780.400.3701
Toll Free: 1.877.547.1017
The project involved 75km of parallel lattice steel 500kV transmission line, spanning from the new Site-C Dam to the Peace Canyon Dam station, which included 3689 helical piles. The pile design required the installation of double-galvanized helical piles installed at both tower hub and anchor locations. The scope of the foundations work included the design, manufacturing, installation, cutting, capping, and proof testing of all helical piles.
The work was completed successfully between November 2018 and January 2021.
“HPS participated in schedule meetings and supported coordination between the two groups that would ultimately allow our other construction activities to continue uninterrupted. The team at HPS was instrumental in meeting the in-service date for the most time sensitive component of this powerline project – the completion of BC Hydro’s 5L005.”
HPS presented a helical pile design solution to replace the existing foundation design. Our Helical pile design offered a more efficient foundation installation with minimal ground disturbance.
HPS and the Prime Contractor designed an optimized double galvanized pile which met BC Hydro’s design life criteria, while also meeting their tower design criteria. HPS also performed additional testing to verify the design in all soil conditions.
Design specifics included:
Our work was completed on time and to BC Hydro and the Prime Contractor satisfaction. Even with project delays, unseasonal temperatures, and difficult access requirements, HPS was able to exceed schedule requirements.
The project involved 75km of parallel lattice steel 500kV transmission line, spanning from the new Site-C Dam to the Peace Canyon Dam station, which included 3689 helical piles. The pile design required the installation of double-galvanized helical piles installed at both tower hub and anchor locations. The scope of the foundations work included the design, manufacturing, installation, cutting, capping, and proof testing of all helical piles.
The work was completed successfully between November 2018 and January 2021.
“HPS participated in schedule meetings and supported coordination between the two groups that would ultimately allow our other construction activities to continue uninterrupted. The team at HPS was instrumental in meeting the in-service date for the most time sensitive component of this powerline project – the completion of BC Hydro’s 5L005.”
HPS presented a helical pile design solution to replace the existing foundation design. Our Helical pile design offered a more efficient foundation installation with minimal ground disturbance.
HPS and the Prime Contractor designed an optimized double galvanized pile which met BC Hydro’s design life criteria, while also meeting their tower design criteria. HPS also performed additional testing to verify the design in all soil conditions.
Design specifics included:
Our work was completed on time and to BC Hydro and the Prime Contractor satisfaction. Even with project delays, unseasonal temperatures, and difficult access requirements, HPS was able to exceed schedule requirements.
Corporate Office
1511 Sparrow Drive
Nisku, AB Canada T9E 8H9
T: 780.400.3700 | F: 780.400.3701
Manufacturing Facility
1511 Sparrow Drive
Nisku, AB Canada T9E 8H9
T: 780.400.3700 | F: 780.400.3701
Toll Free: 1.877.547.1017
Our website uses non-privacy intrusive cookies in accordance with the Cookies Policy contained in Section 10 of our Privacy Policy.
Using our website means these cookies will be stored on your device.
Please review our Cookies Policy for information on how to opt out of receiving these cookies.